Every product is different. That means every project has a different production schedule. To give you an idea of the lead times needed, we have provided a ‘standard’ timetable below.
Allow around 6 months from the placement of the order
In most cases the overall process, from placement of the order through to the production of the initial prototypes, takes around 6 months.
1. Detailed engineering and mould structure 2. Mould building 3. Sample moulding and measurement reports 4. Evaluation of outturn samples by customer 5. Possible adjustments to mould 6. New outturn samples 7. Approval by customer 8. Start of 0-series production | 1 month 3 months 1-2 weeks 2-4 weeks 2 weeks 1-2 weeks 2 weeks |